Tirunelveli: Having started commercial generation, the first unit of the Kudankulam nuclear power project (KKNPP) will not be stopped except for refuelling purposes, said site director, Mr R.S. Sundar. Speaking to mediapersons at Anuvijay Township, the KKNPP officers residential quarters, 16 km from the power plant, on Wednesday, he said the 1,000 MWe first reactor that commenced commercial production from zero hour Wednesday, was functioning well with its maximum generation capacity of 1,000 MWe. “As the plant was given clearance for commercial production after a series of successful tests, it will not be stopped except for refuelling,” said Mr Sundar.

It has been said after continuous operation for 10 months, the plant will be shut down maximum for one-and-a-half months for annual maintenance. “During this suspension period, one-third of the fuel rods will be replaced,” explained the site director, who added that the spent fuel rods replaced from the reactor core will be safely stored in the borated water pool near the primary containment. “The spent fuel can be stored safely to a maximum of seven years,” he informed.

The 335 crore units generated by the first unit in a cumulative 5,266 running hours of the turbine generator has been distributed to the states at a cost of Rs1.22 per unit since the unit attained first criticality on July 2013. This infirm fetched NPCIL Rs350 crore as revenue. However, as the plant began commercial production, the unit cost will be Rs 4 for the beneficiary states, said Mr Sundar. The exact project cost for the first two reactors increased beyond Rs17,000 crore, he explained.

While performing to its maximum capacity, the first unit will produce 2.4 crore units per day, which is capable of fulfilling the energy consumption of 3,600 villages, according to Mr Sundar, who said the power produced at KKNPP will be evacuated through four feeders through the 400 KV power sub-station at Abishegapatty, near Tirunelveli.

 

 

 

Popular articles

13 October 2011

NPP Kudankulam constructed in india meets...

    NPP Kudankulam, which is being constructed in India with Russian assistance, meets all international safety requirements and the people of Tamil Nadu...
19 August 2011

IAF's Sukhoi jets to be upgraded to fifth...

     India's air superiority Sukhoi-30MKI fighters will soon be converted into 'Super Sukhois' by upgrading them with fifth generation combat jet...
08 August 2011

Kudankulam gets Uranium for next 5 years

       The Kudankulam Nuclear Plant has received uranium fuel bundles from Russia for the next five years as the plant needs 25-30 tonnes of fuel per year...
Emergency phone number only for the citizens of Russia in emergency in India +91-81-3030-0551
Address:
Shantipath, Chanakyapuri,
New Delhi - 110021
Telephones:
(91-11) 2611-0640/41/42;
(91-11) 2687 38 02;
(91-11) 2687 37 99
E-mail:
This email address is being protected from spambots. You need JavaScript enabled to view it.
This email address is being protected from spambots. You need JavaScript enabled to view it.