Kudankulam-II to be commissioned in 6-8 months: P.S. Raghavan, Indian envoy to Russia

Friday, 17 July 2015 08:29

Raghavan said work was underway on the unit-II of Kudankulam Nuclear Power Plant which will have the capacity to generate 1,000 MW of electricity.
MOSCOW: The second unit of the Kudankulam Nuclear Power Plant in Tamil Nadu will be commissioned in the next 6-8 months amid efforts to expedite the setting up of 12 atomic plants proposed to be built by Russia in India in two decades.
Giving this information here, Indian Ambassador to Russia P S Raghavan said discussions are underway on the units III, IV, V and VI to be built at Kudankulam.
Process is also underway to identify a site in Karnataka and Andhra Pradesh for a plant which was proposed to be set up in Haripur in West Bengal but could not materialise due to various factors, including protests by locals.
"We are committed to the Russians... In last December (during the visit of PresidentVladimir Putin to India), we had decided that we will speed up the nuclear plant manufacture and that in two decades, we will have 12 power plants," Raghavan told PTI in an interview here.
Asked about the progress on unit-II of Kudankulam Nuclear Power Plant (KNPP) which is behind schedule, he said work is underway on the unit which will have the capacity to generate 1,000 MW of electricity.
"Hot run is already going on...I would say that in the next 6-8 months, it should be fully commissioned. It should be onstream," the Ambassador said.
"There has been a little bit of delay but that is not significant delay," he said.
Commissioning of the unit-II has been put off four times so far. The last time the Nuclear Power Corporation of India Limited (NPCIL) had postponed putting the unit into commercial operation was this month.
On the causes for the delay, the Indian Ambassador said part of it was that after Fukushima radiation exposure of 2011, there has been a "progressive tightening" of safety regulations by the Atomic Energy Regulatory Board (AERB).
"As you go along, they specify more tests, more shutdown periods and longer test-running," he said.
Besides, part of the delay was on account of "their equipment matching with our equipment", Raghavan said.
With regard to units III and IV, he said 'long cycle' contracts have been done. "So, it is going well," Raghavan said, adding that, "we are already talking about how to do unit V and VI."
He said that work is also underway to identify another site for Russian nuclear plants, in place of Haripur in West Bengal where problems had erupted.
"Some places have been identified... Karnataka and Andhra Pradesh have shown interest in nuclear power plants," Raghavan said.


economictimes.indiatimes.com, 17.07.2015

Popular articles

01 March 2018

Presidential Address to the Federal Assembly

The President of Russia delivered the Address to the Federal Assembly. The ceremony took place at the Manezh Central Exhibition Hall. The presentation of...
31 March 2018

Russia’s questions to the United Kingdom regarding the...

On March 31, the Embassy of the Russian Federation in London delivered to the British Foreign Ministry a note with a list of questions to the British side...
14 April 2018

Statement by President of Russia Vladimir Putin

On April 14, the United States, supported by its allies, launched an airstrike against military and civilian targets in the Syrian Arab Republic. An act...
Emergency phone number only for the citizens of Russia in emergency in India +91-81-3030-0551
Address:
Shantipath, Chanakyapuri,
New Delhi - 110021
Telephones:
(91-11) 2611-0640/41/42;
(91-11) 2687 38 02;
(91-11) 2687 37 99
E-mail:
This email address is being protected from spambots. You need JavaScript enabled to view it.
This email address is being protected from spambots. You need JavaScript enabled to view it.